ITAC Assessment: MA0508
ITAC logo
ITAC Assessment: MA0508
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Extrusion plastic
NAICS
n/a
SIC 3082: Unsupported Plastics Profile Shapes
Sales Range $10
M
to 50
M
# of Employees 208
Plant Area 120,000
ft2
Annual Production 1,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $341,806 4,651,000
kWh
Electricity Demand $47,535 9,149
kW-mo/yr
Electricity Fees $2,268 -
LPG $7,489 641
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,379 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $43,537

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Personnel Changes Savings
01 2.6218: Turn off equipment when not in use $29,135 - $65,635
995,738
kWh
- $(-36,500.0)
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,830 $5,950 $5,830
85,819
kWh
- -
03 2.7111: Reduce illumination to minimum necessary levels $4,878 $3,513 $4,878
69,602
kWh
- -
04 2.7224: Reduce space conditioning during non-working hours $2,108 $400 - $2,108
-
MMBtu
-
05 2.6218: Turn off equipment when not in use $1,586 - $1,586
22,623
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $842 $1,000 $842
12,398
kWh
- -
TOTAL RECOMMENDED $44,379 $10,863 $78,771
1,186,180
kWh
$2,108
-
MMBtu
$(-36,500.0)
TOTAL IMPLEMENTED $43,537 $9,863 $77,929
1,173,782
kWh
$2,108
-
MMBtu
$(-36,500.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings LPG Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs