ITAC Assessment: MA0507
ITAC logo
ITAC Assessment: MA0507
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Electronic Components and Assemblies
NAICS
n/a
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 215
Plant Area 150,000
ft2
Annual Production 50,000
lb
Production Hrs. Annual 4,992
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $268,370 4,767,840
kWh
Electricity Demand $117,391 9,753
kW-mo/yr
Electricity Fees $35,124 -
Natural Gas $74,207 8,486
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $93,109 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $71,328

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 4.212: Adopt in-house material generation $69,744 $194,100 $(-3,189.0)
(-56,132)
kWh
$(-511.0)
-
kW-mo/yr
- - $(-1,000.0) $74,444 -
02 2.6231: Utilize controls to operate equipment only when needed $12,237 $40,000 $1,509
29,700
kWh
- $10,728
-
MMBtu
- - - -
03 2.4131: Size electric motors for peak operating efficiency $4,940 $4,000 $3,112
51,546
kWh
$1,828
-
kW-mo/yr
- - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,037 $35,500 $2,657
44,928
kWh
$1,380
-
kW-mo/yr
- - - - -
05 3.4114: Replace city water with recycled water via cooling tower $795 $3,230 - - - $795
-
Tgal
- - -
06 4.821: Pay bills on time to avoid late fees $576 - - - - - - - $576
07 2.3137: Use power during off-peak periods $567 $500 - - - - - - $567
08 2.6218: Turn off equipment when not in use $213 - $124
2,141
kWh
$89
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $93,109 $277,330 $4,213
72,183
kWh
$2,786
-
kW-mo/yr
$10,728
-
MMBtu
$795
-
Tgal
$(-1,000.0) $74,444 $1,143
TOTAL IMPLEMENTED $71,328 $197,330 $(-3,065.0)
(-53,991)
kWh
$(-422.0)
-
kW-mo/yr
- $795
-
Tgal
$(-1,000.0) $74,444 $576
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs