| Assessment Year | 2017 |
|---|---|
| Principal Product | Treated wastewater |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $1 M to 5M |
| # of Employees | 5 |
| Plant Area |
165,000
ft2
|
| Annual Production | 1,642,500
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $193,175 | 3,967,397 |
kWh
|
$0.049 | |
| Electricity Demand | $75,425 | 6,236 |
kW-mo/yr
|
$12.10 | |
| Electricity Fees | $0.0 | - |
|
- | |
| Natural Gas | $57,087 | 11,149 |
MMBtu
|
$5.12 | |
| Waste Disposal Costs | |||||
| Water Usage | $36,043 | 6,032,291 |
Tgal
|
$0.006 | |
| TOTAL YEARLY COSTS | $361,730 | ||||
| RECOMMENDED SAVINGS* | $51,864 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $29,215 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.7311: Maintain machines to reduce leaks | $16,398 | $20,000 |
$12,237
251,324
kWh
|
$4,161
-
kW-mo/yr
|
- | |
| 02 | 2.9111: Use solar heat to heat make-up air | $13,132 | $72,000 |
$13,132
269,711
kWh
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,735 | $23,350 |
$4,284
87,989
kWh
|
$1,451
-
kW-mo/yr
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,449 | $332 |
$4,066
83,500
kWh
|
$1,384
-
kW-mo/yr
|
- | |
| 05 | 2.7231: Use radiant heater for spot heating | $4,330 | $1,815 | - | - |
$4,330
-
MMBtu
|
|
| 06 | 2.7135: Install occupancy sensors | $3,167 | $1,660 |
$2,363
48,532
kWh
|
$804
-
kW-mo/yr
|
- | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,956 | - |
$827
16,988
kWh
|
$1,129
-
kW-mo/yr
|
- | |
| 08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,082 | $3,200 |
$756
15,516
kWh
|
$327
-
kW-mo/yr
|
- | |
| 09 | 2.7134: Use photocell controls | $615 | $73 |
$459
9,424
kWh
|
$156
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $51,864 | $122,430 |
$38,123
782,984
kWh
|
$9,411
-
kW-mo/yr
|
$4,330
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $29,215 | $25,347 |
$17,885
367,328
kWh
|
$7,000
-
kW-mo/yr
|
$4,330
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs