| Assessment Year | 2001 |
|---|---|
| Principal Product | Moldings and picture frames |
| NAICS |
n/a
|
| SIC | 2431: Millwork |
| Sales Range | $5 M to 10M |
| # of Employees | 50 |
| Plant Area |
29,000
ft2
|
| Annual Production | 3,900
thousand feet
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | New Hampshire |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $69,899 | 1,010,700 |
kWh
|
$0.069 |
| Electricity Demand | $22,945 | 2,490 |
kW-mo/yr
|
$9.21 |
| Electricity Fees | $2,221 | - |
|
- |
| LPG | $2,352 | 167 |
MMBtu
|
$14.08 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,210 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,230 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $1,900 | - |
$1,900
22,218
kWh
|
- | |
| 02 | 2.3212: Optimize plant power factor | $1,530 | $2,100 | - |
$1,530
-
kW-mo/yr
|
|
| 03 | 2.4221: Install compressor air intakes in coolest locations | $500 | $600 |
$500
6,000
kWh
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $460 | - |
$460
5,363
kWh
|
- | |
| 05 | 2.6218: Turn off equipment when not in use | $450 | - |
$450
4,500
kWh
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $370 | $100 |
$370
4,300
kWh
|
- | |
| TOTAL RECOMMENDED | $5,210 | $2,800 |
$3,680
42,381
kWh
|
$1,530
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $3,230 | $700 |
$3,230
37,881
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs