| Assessment Year | 2001 |
|---|---|
| Principal Product | Coated film and paper products |
| NAICS |
n/a
|
| SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 59 |
| Plant Area |
82,000
ft2
|
| Annual Production | 660,000
thousand feet
|
| Production Hrs. Annual | 6,048
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $120,168 | 1,801,120 |
kWh
|
$0.067 |
| Electricity Demand | $37,366 | 6,850 |
kW-mo/yr
|
$5.45 |
| Electricity Fees | $1,146 | - |
|
- |
| Natural Gas | $201,362 | 30,858 |
MMBtu
|
$6.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $60,353 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,486 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.212: Adopt in-house material generation | $48,702 | $180,000 |
$(-34,742.0)
(-451,200)
kWh
|
$(-4,556.0)
-
kW-mo/yr
|
- | $(-3,000.0) | $91,000 | |
| 02 | 2.7224: Reduce space conditioning during non-working hours | $2,846 | - | - | - |
$2,846
-
MMBtu
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,613 | $150 |
$5,613
72,900
kWh
|
- | - | - | - | |
| 04 | 2.3212: Optimize plant power factor | $2,165 | $3,750 | - |
$2,165
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $516 | $1,000 |
$516
6,700
kWh
|
- | - | - | - | |
| 06 | 2.7224: Reduce space conditioning during non-working hours | $161 | $100 | - | - |
$161
-
MMBtu
|
- | - | |
| 07 | 4.821: Pay bills on time to avoid late fees | $350 | - | - | - | - | $350 | - | |
| TOTAL RECOMMENDED | $60,353 | $185,000 |
$(-28,613.0)
(-371,600)
kWh
|
$(-2,391.0)
-
kW-mo/yr
|
$3,007
-
MMBtu
|
$(-2,650.0) | $91,000 | ||
| TOTAL IMPLEMENTED | $9,486 | $1,250 |
$6,129
79,600
kWh
|
- |
$3,007
-
MMBtu
|
$350 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs