ITAC Assessment: MA0493
ITAC logo
ITAC Assessment: MA0493
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Coated film and paper products
NAICS
n/a
SIC 2672: Coated and Laminated Paper, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 59
Plant Area 82,000
ft2
Annual Production 660,000
thousand feet
Production Hrs. Annual 6,048
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $120,168 1,801,120
kWh
Electricity Demand $37,366 6,850
kW-mo/yr
Electricity Fees $1,146 -
Natural Gas $201,362 30,858
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $60,353 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,486

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 4.212: Adopt in-house material generation $48,702 $180,000 $(-34,742.0)
(-451,200)
kWh
$(-4,556.0)
-
kW-mo/yr
- $(-3,000.0) $91,000
02 2.7224: Reduce space conditioning during non-working hours $2,846 - - - $2,846
-
MMBtu
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,613 $150 $5,613
72,900
kWh
- - - -
04 2.3212: Optimize plant power factor $2,165 $3,750 - $2,165
-
kW-mo/yr
- - -
05 2.4221: Install compressor air intakes in coolest locations $516 $1,000 $516
6,700
kWh
- - - -
06 2.7224: Reduce space conditioning during non-working hours $161 $100 - - $161
-
MMBtu
- -
07 4.821: Pay bills on time to avoid late fees $350 - - - - $350 -
TOTAL RECOMMENDED $60,353 $185,000 $(-28,613.0)
(-371,600)
kWh
$(-2,391.0)
-
kW-mo/yr
$3,007
-
MMBtu
$(-2,650.0) $91,000
TOTAL IMPLEMENTED $9,486 $1,250 $6,129
79,600
kWh
- $3,007
-
MMBtu
$350 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs