ITAC Assessment: AM0868
ITAC logo
ITAC Assessment: AM0868
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Christian disciples
NAICS 813110: Religious Organizations
SIC 8661: Religious Organizations
Sales Range less than $500
k
# of Employees 8
Plant Area 68,622
ft2
Annual Production 120
pieces
Production Hrs. Annual 2,600
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $15,543 388,580
kWh
Electricity Demand $20,120 1,562
kW-mo/yr
Natural Gas $5,919 606
MMBtu
Waste Disposal Costs
Water Usage $326 63
Tgal
TOTAL YEARLY COSTS $41,908
RECOMMENDED SAVINGS* $5,625 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,415 $26,260 $1,239
30,984
kWh
$3,176
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $503 $13,225 $503
12,574
kWh
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $487 $4,000 $487
12,175
kWh
- -
04 2.7261: Install timers and/or thermostats $220 $1,800 $150
3,732
kWh
- $70
-
MMBtu
TOTAL RECOMMENDED $5,625 $45,285 $2,379
59,465
kWh
$3,176
-
kW-mo/yr
$70
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs