ITAC Assessment: MA0490
ITAC logo
ITAC Assessment: MA0490
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Structural fasteners
NAICS
n/a
SIC 3452: Bolts, Nuts, Screws, Rivets, and Washers
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 83,000
ft2
Annual Production 25,000
ton
Production Hrs. Annual 8,400
hrs
Location (State) Vermont

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $244,382 5,820,400
kWh
Electricity Demand $165,105 10,985
kW-mo/yr
Electricity Fees $19,140 -
Natural Gas $189,118 29,963
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,198 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,848

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Consumption Savings
01 2.7311: Ventilation system to shut off when room is not in use $7,248 - - - $7,248
-
MMBtu
-
02 2.2437: Recover waste heat from equipment $6,500 $14,500 - - $6,500
-
MMBtu
-
03 2.7111: Reduce illumination to minimum necessary levels $3,500 $390 $2,300
54,600
kWh
$1,200
-
kW-mo/yr
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $2,350 $5,000 $2,350
62,000
kWh
- - -
05 3.4116: Meter recycled water (to reduce sewer charges) $1,500 $6,000 - - - $1,500
-
Tgal
06 2.4221: Install compressor air intakes in coolest locations $1,100 $1,000 $1,100
26,500
kWh
- - -
07 2.7224: Reduce space conditioning during non-working hours $1,000 - - - $1,000
-
MMBtu
-
TOTAL RECOMMENDED $23,198 $26,890 $5,750
143,100
kWh
$1,200
-
kW-mo/yr
$14,748
-
MMBtu
$1,500
-
Tgal
TOTAL IMPLEMENTED $12,848 $1,390 $3,400
81,100
kWh
$1,200
-
kW-mo/yr
$8,248
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs