Assessment Year | 2001 |
---|---|
Principal Product | Corrugated Cardboard |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
200,000
ft2
|
Annual Production | 720,000
thousand feet
|
Production Hrs. Annual | 6,552
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $266,253 | 4,495,000 |
kWh
|
$0.059 |
Electricity Demand | $78,214 | 13,356 |
kW-mo/yr
|
$5.86 |
Electricity Fees | $807 | - |
|
- |
Natural Gas | $270,588 | 46,510 |
MMBtu
|
$5.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $78,060 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,040 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Water Disposal Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $19,400 | $93,000 | - | - |
$26,100
-
MMBtu
|
$(-6,700.0)
-
MMBtu
|
- | - | |
02 | 2.3212: Optimize plant power factor | $15,900 | $13,000 | - |
$15,900
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7224: Reduce space conditioning during non-working hours | $8,590 | $30,000 | - | - |
$8,590
-
MMBtu
|
- | - | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $7,900 | $23,000 | - | - |
$7,900
-
MMBtu
|
- | - | - | |
05 | 2.7231: Use radiant heater for spot heating | $5,430 | $25,000 | - | - |
$5,430
-
MMBtu
|
- | - | - | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,200 | $13,000 | - | - |
$5,200
-
MMBtu
|
- | - | - | |
07 | 3.5131: Recycle white water | $5,000 | $20,000 | - | - | - | - |
$3,000
-
Tgal
|
$2,000
-
Tgal
|
|
08 | 3.4155: Meter waste water | $4,400 | $12,000 | - | - | - | - |
$4,400
-
Tgal
|
- | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,040 | $450 |
$2,040
34,100
kWh
|
- | - | - | - | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,700 | $5,000 |
$1,700
28,000
kWh
|
- | - | - | - | - | |
11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,500 | $7,000 |
$1,500
24,900
kWh
|
- | - | - | - | - | |
12 | 2.7132: Install timers on light switches in little used areas | $1,000 | $600 |
$1,000
18,300
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $78,060 | $242,050 |
$6,240
105,300
kWh
|
$15,900
-
kW-mo/yr
|
$53,220
-
MMBtu
|
$(-6,700.0)
-
MMBtu
|
$7,400
-
Tgal
|
$2,000
-
Tgal
|
||
TOTAL IMPLEMENTED | $2,040 | $450 |
$2,040
34,100
kWh
|
- | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Water Disposal Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs