Assessment Year | 2000 |
---|---|
Principal Product | plastic profiles and sheets |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 88 |
Plant Area |
110,000
ft2
|
Annual Production | 3,500
ton
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $187,601 | 8,804,400 |
kWh
|
$0.021 |
Electricity Demand | $103,759 | 20,640 |
kW-mo/yr
|
$5.03 |
Electricity Fees | $66 | - |
|
- |
Natural Gas | $8,954 | 4,615 |
MMBtu
|
$1.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,484 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $2,828 | $6,750 |
$2,166
117,234
kWh
|
$662
-
kW-mo/yr
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $2,466 | $2,560 |
$1,469
79,426
kWh
|
$997
-
kW-mo/yr
|
- | |
03 | 2.2511: Insulate bare equipment | $2,117 | $3,116 |
$1,709
92,321
kWh
|
$599
-
kW-mo/yr
|
$(-191.0)
-
MMBtu
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,081 | $90 |
$787
42,497
kWh
|
$294
-
kW-mo/yr
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $618 | $494 |
$450
24,326
kWh
|
$168
-
kW-mo/yr
|
- | |
06 | 2.2437: Recover waste heat from equipment | $374 | $230 | - | - |
$374
-
MMBtu
|
|
TOTAL RECOMMENDED | $9,484 | $13,240 |
$6,581
355,804
kWh
|
$2,720
-
kW-mo/yr
|
$183
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs