Assessment Year | 2000 |
---|---|
Principal Product | Braiding Machines |
NAICS |
n/a
|
SIC | 3552: Textile Machinery |
Sales Range | $10 M to 50M |
# of Employees | 240 |
Plant Area |
270,000
ft2
|
Annual Production | 500
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Rhode Island |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $101,272 | 1,508,206 |
kWh
|
$0.067 |
Electricity Demand | $7,929 | 4,887 |
kW-mo/yr
|
$1.62 |
Electricity Fees | $8,915 | - |
|
- |
Natural Gas | $32,761 | 5,394 |
MMBtu
|
$6.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,243 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,155 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,392 | $17,000 |
$3,392
43,962
kWh
|
- | - | - | |
02 | 2.7124: Make a practice of turning off lights when not needed | $1,357 | - |
$1,357
17,585
kWh
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,374 | $1,010 |
$2,374
30,774
kWh
|
- | - | - | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $3,400 | $12,780 |
$3,400
43,962
kWh
|
- | - | - | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $696 | $1,495 |
$995
12,896
kWh
|
$79
-
kW-mo/yr
|
$(-378.0)
-
MMBtu
|
- | |
06 | 3.8214: Use water-based developers and finishers | $527 | $960 | - | - | - |
$527
-
gal
|
|
07 | 2.4221: Install compressor air intakes in coolest locations | $497 | $750 |
$497
6,448
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $12,243 | $33,995 |
$12,015
155,627
kWh
|
$79
-
kW-mo/yr
|
$(-378.0)
-
MMBtu
|
$527
-
gal
|
||
TOTAL IMPLEMENTED | $8,155 | $15,500 |
$7,628
98,769
kWh
|
- | - |
$527
-
gal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs