| Assessment Year | 2021 |
|---|---|
| Principal Product | OTC Medicine |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $50 M to 100M |
| # of Employees | 500 |
| Plant Area |
628,000
ft2
|
| Annual Production | 500,000,000
units
|
| Production Hrs. Annual | 6,400
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $497,741 | 20,346,033 |
kWh
|
$0.024 | |
| Electricity Demand | $742,529 | 36,603 |
kW-mo/yr
|
$20.29 | |
| Electricity Fees | $88,647 | - |
|
- | |
| Natural Gas | $377,385 | 87,798 |
MMBtu
|
$4.30 | |
| Waste Disposal Costs | |||||
| Water Usage | $62,394 | 21,766 |
Tgal
|
$2.87 | |
| Water Disposal | $48,826 | 21,766 |
Tgal
|
$2.24 | |
| TOTAL YEARLY COSTS | $1,817,522 | ||||
| RECOMMENDED SAVINGS* | $34,197 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $19,602 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.4155: Meter waste water | $9,914 | $580 | - | - |
$9,914
-
Tgal
|
- | - | |
| 02 | 2.3137: Use power during off-peak periods | $9,080 | $70 | - |
$9,080
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $4,939 | $70 |
$2,314
94,448
kWh
|
$2,625
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.4155: Meter waste water | $3,714 | $580 | - | - |
$3,714
-
Tgal
|
- | - | |
| 05 | 3.5311: Recover and reuse waste material | $3,432 | $3,500 | - | - | - | $840 | $2,592 | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,556 | $2,500 |
$2,216
90,462
kWh
|
- | - | $(-560.0) | $(-100.0) | |
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $967 | $1,650 |
$383
15,624
kWh
|
$584
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.7135: Install occupancy sensors | $595 | $1,289 |
$595
24,284
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $34,197 | $10,239 |
$5,508
224,818
kWh
|
$12,289
-
kW-mo/yr
|
$13,628
-
Tgal
|
$280 | $2,492 | ||
| TOTAL IMPLEMENTED | $19,602 | $7,429 |
$5,125
209,194
kWh
|
$11,705
-
kW-mo/yr
|
- | $280 | $2,492 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs