| Assessment Year | 2000 |
|---|---|
| Principal Product | PVC and Non-PVC Compounds |
| NAICS |
n/a
|
| SIC | 3087: Custom Compounding of Purchased Plastics Resins |
| Sales Range | $100 M to 500M |
| # of Employees | 200 |
| Plant Area |
100,000
ft2
|
| Annual Production | 91,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $717,786 | 10,814,478 |
kWh
|
$0.066 |
| Electricity Demand | $93,283 | 25,698 |
kW-mo/yr
|
$3.63 |
| Electricity Fees | $807 | - |
|
- |
| LPG | $30,449 | 4,451 |
MMBtu
|
$6.84 |
| Fuel Oil #4 | $80,917 | 18,714 |
MMBtu
|
$4.32 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,415 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $27,099 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,467 | $640 |
$13,917
111,079
kWh
|
$1,550
-
kW-mo/yr
|
- | - | |
| 02 | 2.2625: Chill water to the highest temperature possible | $6,077 | $4,000 |
$6,077
97,011
kWh
|
- | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $2,974 | $4,200 | - |
$294
-
kW-mo/yr
|
$2,680
-
MMBtu
|
- | |
| 04 | 2.2123: Insulate feedwater tank | $1,316 | $800 | - | - |
$1,316
-
MMBtu
|
- | |
| 05 | 2.2511: Insulate bare equipment | $1,140 | $1,500 | - | - |
$1,140
-
MMBtu
|
- | |
| 06 | 3.4131: Minimize contamination of water before treatment | $951 | $500 | - | - |
$929
-
MMBtu
|
$22
-
lb
|
|
| 07 | 2.2123: Insulate feedwater tank | $490 | $1,100 | - | - |
$490
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $28,415 | $12,740 |
$19,994
208,090
kWh
|
$1,844
-
kW-mo/yr
|
$6,555
-
MMBtu
|
$22
-
lb
|
||
| TOTAL IMPLEMENTED | $27,099 | $11,940 |
$19,994
208,090
kWh
|
$1,844
-
kW-mo/yr
|
$5,239
-
MMBtu
|
$22
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs