Assessment Year | 1996 |
---|---|
Principal Product | Beef |
NAICS |
n/a
|
SIC | 2011: Meat Packing Plants |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
40,000
ft2
|
Annual Production | 52,000
units
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $105,649 | 2,536,635 |
kWh
|
$0.042 |
Electricity Demand | $16,911 | 4,884 |
kW-mo/yr
|
$3.46 |
LPG | $21,728 | 3,175 |
MMBtu
|
$6.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,396 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,055 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,419 | $779 |
$1,274
30,774
kWh
|
$145
-
kW-mo/yr
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $2,087 | $2,971 |
$1,808
43,376
kWh
|
$279
-
kW-mo/yr
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,147 | $650 |
$1,147
27,550
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,417 | $450 |
$1,417
29,308
kWh
|
- | - | |
05 | 2.2621: Modify refrigeration system to operate at a lower pressure | $1,922 | $6,000 |
$1,922
44,549
kWh
|
- | - | |
06 | 3.6192: Use a less expensive method of waste removal | $1,404 | - | - | - |
$1,404
-
lb
|
|
TOTAL RECOMMENDED | $9,396 | $10,850 |
$7,568
175,557
kWh
|
$424
-
kW-mo/yr
|
$1,404
-
lb
|
||
TOTAL IMPLEMENTED | $6,055 | $4,071 |
$4,372
100,234
kWh
|
$279
-
kW-mo/yr
|
$1,404
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs