Assessment Year | 2000 |
---|---|
Principal Product | Carbon Seals and Bearings |
NAICS |
n/a
|
SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
55,000
ft2
|
Annual Production | 600,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Rhode Island |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $405,593 | 6,592,907 |
kWh
|
$0.062 |
Electricity Demand | $36,016 | 12,720 |
kW-mo/yr
|
$2.83 |
Electricity Fees | $3,134 | - |
|
- |
Natural Gas | $82,243 | 16,113 |
MMBtu
|
$5.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $118,531 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,769 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $69,572 | $286,600 |
$88,211
1,379,543
kWh
|
$7,191
-
kW-mo/yr
|
$(-25,830.0)
-
MMBtu
|
- | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $22,135 | $42,000 |
$27,923
436,694
kWh
|
$2,377
-
kW-mo/yr
|
$(-8,165.0)
-
MMBtu
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,240 | $26,115 |
$6,240
97,597
kWh
|
- | - | - | |
04 | 2.2692: Use outside cold water source as a supply of cooling water | $5,388 | $13,800 |
$4,966
77,667
kWh
|
$422
-
kW-mo/yr
|
- | - | |
05 | 2.7313: Recycle air for heating, ventilation and air conditioning | $4,828 | $1,960 |
$2,755
43,083
kWh
|
- |
$7,353
-
MMBtu
|
$(-5,280.0) | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,880 | $32,900 |
$4,498
70,340
kWh
|
$382
-
kW-mo/yr
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,435 | $300 |
$2,435
45,721
kWh
|
- | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $1,423 | $1,070 |
$1,423
22,274
kWh
|
- | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $815 | $3,075 |
$750
11,723
kWh
|
$65
-
kW-mo/yr
|
- | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $815 | $300 |
$750
11,723
kWh
|
$65
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $118,531 | $408,120 |
$139,951
2,196,365
kWh
|
$10,502
-
kW-mo/yr
|
$(-26,642.0)
-
MMBtu
|
$(-5,280.0) | ||
TOTAL IMPLEMENTED | $19,769 | $50,330 |
$16,827
270,808
kWh
|
$869
-
kW-mo/yr
|
$7,353
-
MMBtu
|
$(-5,280.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs