Assessment Year | 1999 |
---|---|
Principal Product | Dimensional Measurement Instrumentation |
NAICS |
n/a
|
SIC | 3825: Instruments for Measuring and Testing of Electricity and Electrical Signals |
Sales Range | $50 M to 100M |
# of Employees | 380 |
Plant Area |
143,300
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,846
hrs
|
Location (State) | Rhode Island |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $253,587 | 4,267,585 |
kWh
|
$0.059 |
Electricity Demand | $36,817 | 11,097 |
kW-mo/yr
|
$3.32 |
Electricity Fees | $4,117 | - |
|
- |
Natural Gas | $37,595 | 7,503 |
MMBtu
|
$5.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $94,793 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,324 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $30,897 | $36,700 |
$44,710
731,243
kWh
|
$3,388
-
kW-mo/yr
|
$(-17,201.0)
-
MMBtu
|
- | |
02 | 2.2511: Insulate bare equipment | $30,690 | $820 |
$30,690
499,707
kWh
|
- | - | - | |
03 | 3.4114: Replace city water with recycled water via cooling tower | $14,463 | $20,800 |
$6,433
105,217
kWh
|
$382
-
kW-mo/yr
|
- |
$7,648
-
Tgal
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,237 | $3,575 |
$1,075
17,585
kWh
|
- |
$8,162
-
MMBtu
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,234 | $12,279 |
$3,008
49,238
kWh
|
$226
-
kW-mo/yr
|
- | - | |
06 | 2.7311: Ventilation system to shut off when room is not in use | $2,849 | - |
$559
9,086
kWh
|
- |
$2,290
-
MMBtu
|
- | |
07 | 2.7229: Air condition only space necessary | $1,137 | $2,670 | - | - |
$1,137
-
MMBtu
|
- | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $930 | $4,225 |
$770
12,603
kWh
|
$160
-
kW-mo/yr
|
- | - | |
09 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $718 | $2,000 |
$1,004
16,413
kWh
|
$76
-
kW-mo/yr
|
$(-362.0)
-
MMBtu
|
- | |
10 | 2.4221: Install compressor air intakes in coolest locations | $638 | $300 |
$638
7,913
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $94,793 | $83,369 |
$88,887
1,449,005
kWh
|
$4,232
-
kW-mo/yr
|
$(-5,974.0)
-
MMBtu
|
$7,648
-
Tgal
|
||
TOTAL IMPLEMENTED | $28,324 | $27,345 |
$8,705
139,801
kWh
|
$382
-
kW-mo/yr
|
$11,589
-
MMBtu
|
$7,648
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs