| Assessment Year | 1999 |
|---|---|
| Principal Product | Steel Mill Equipment |
| NAICS |
n/a
|
| SIC | 3457: |
| Sales Range | $10 M to 50M |
| # of Employees | 380 |
| Plant Area |
250,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $482,750 | 7,486,518 |
kWh
|
$0.064 |
| Electricity Demand | $59,369 | 16,355 |
kW-mo/yr
|
$3.63 |
| Natural Gas | $15,534 | 2,669 |
MMBtu
|
$5.82 |
| Fuel Oil #4 | $92,674 | 27,710 |
MMBtu
|
$3.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $140,665 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,303 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #4 Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.631: Install an uninteruptable power supply | $120,000 | $24,000 | - | - | - | - | $120,000 | |
| 02 | 2.6218: Turn off equipment when not in use | $8,636 | $1,360 | - | - |
$1,235
-
MMBtu
|
$7,401
-
MMBtu
|
- | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,629 | $500 | - | - | - |
$4,629
-
MMBtu
|
- | |
| 04 | 2.3212: Optimize plant power factor | $4,578 | $10,705 | - |
$4,578
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,038 | $1,295 |
$1,038
17,292
kWh
|
- | - | - | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,116 | $3,400 |
$1,116
18,757
kWh
|
- | - | - | - | |
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $668 | $1,244 |
$668
11,137
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $140,665 | $42,504 |
$2,822
47,186
kWh
|
$4,578
-
kW-mo/yr
|
$1,235
-
MMBtu
|
$12,030
-
MMBtu
|
$120,000 | ||
| TOTAL IMPLEMENTED | $14,303 | $3,155 |
$1,038
17,292
kWh
|
- |
$1,235
-
MMBtu
|
$12,030
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #4 Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs