Assessment Year | 1999 |
---|---|
Principal Product | Steel Mill Equipment |
NAICS |
n/a
|
SIC | 3457: |
Sales Range | $10 M to 50M |
# of Employees | 380 |
Plant Area |
250,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $482,750 | 7,486,518 |
kWh
|
$0.064 |
Electricity Demand | $59,369 | 16,355 |
kW-mo/yr
|
$3.63 |
Natural Gas | $15,534 | 2,669 |
MMBtu
|
$5.82 |
Fuel Oil #4 | $92,674 | 27,710 |
MMBtu
|
$3.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $140,665 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,303 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #4 Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.631: Install an uninteruptable power supply | $120,000 | $24,000 | - | - | - | - | $120,000 | |
02 | 2.6218: Turn off equipment when not in use | $8,636 | $1,360 | - | - |
$1,235
-
MMBtu
|
$7,401
-
MMBtu
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,629 | $500 | - | - | - |
$4,629
-
MMBtu
|
- | |
04 | 2.3212: Optimize plant power factor | $4,578 | $10,705 | - |
$4,578
-
kW-mo/yr
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,038 | $1,295 |
$1,038
17,292
kWh
|
- | - | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,116 | $3,400 |
$1,116
18,757
kWh
|
- | - | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $668 | $1,244 |
$668
11,137
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $140,665 | $42,504 |
$2,822
47,186
kWh
|
$4,578
-
kW-mo/yr
|
$1,235
-
MMBtu
|
$12,030
-
MMBtu
|
$120,000 | ||
TOTAL IMPLEMENTED | $14,303 | $3,155 |
$1,038
17,292
kWh
|
- |
$1,235
-
MMBtu
|
$12,030
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #4 Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs