Assessment Year | 1999 |
---|---|
Principal Product | Plastic bottles and labeling |
NAICS |
n/a
|
SIC | 3085: Plastics Bottles |
Sales Range | $10 M to 50M |
# of Employees | 121 |
Plant Area |
67,000
ft2
|
Annual Production | 108,000,000
pieces
|
Production Hrs. Annual | 8,280
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $281,087 | 4,725,381 |
kWh
|
$0.059 |
Electricity Demand | $74,395 | 7,986 |
kW-mo/yr
|
$9.32 |
LPG | $7,591 | 938 |
MMBtu
|
$8.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,753 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,317 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|
01 | 4.114: Add/modify equipment to improve drying process | $18,033 | $25,200 |
$(-3,145.0)
(-52,462)
kWh
|
$(-662.0)
-
kW-mo/yr
|
$21,840 | |
02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $9,704 | $5,262 |
$8,381
140,680
kWh
|
$1,323
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,317 | $3,950 |
$3,317
55,979
kWh
|
- | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $1,414 | - |
$1,414
24,033
kWh
|
- | - | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $1,135 | - |
$1,135
19,050
kWh
|
- | - | |
06 | 4.642: Install sensors to detect and avoid jams | $2,000 | $700 | - | - | $2,000 | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $6,150 | $1,200 | - | - | $6,150 | |
TOTAL RECOMMENDED | $41,753 | $36,312 |
$11,102
187,280
kWh
|
$661
-
kW-mo/yr
|
$29,990 | ||
TOTAL IMPLEMENTED | $3,317 | $3,950 |
$3,317
55,979
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs