| Assessment Year | 1999 |
|---|---|
| Principal Product | tape and CD jewel cases |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
57,800
ft2
|
| Annual Production | 305,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $216,410 | 5,329,133 |
kWh
|
$0.041 |
| Electricity Demand | $149,849 | 9,886 |
kW-mo/yr
|
$15.16 |
| Natural Gas | $4,853 | 509 |
MMBtu
|
$9.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $21,872 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,703 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2612: Use cooling tower water instead of refrigeration | $9,010 | $21,612 |
$5,018
121,336
kWh
|
$3,992
-
kW-mo/yr
|
|
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,201 | $18,690 |
$6,201
138,628
kWh
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,159 | $7,290 |
$2,133
52,169
kWh
|
$1,026
-
kW-mo/yr
|
|
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,860 | - |
$2,860
69,168
kWh
|
- | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $642 | $2,137 |
$642
15,533
kWh
|
- | |
| TOTAL RECOMMENDED | $21,872 | $49,729 |
$16,854
396,834
kWh
|
$5,018
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $9,703 | $20,827 |
$9,703
223,329
kWh
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs