Assessment Year | 2005 |
---|---|
Principal Product | Fire Truck Parts |
NAICS | 334419: Other Electronic Component Manufacturing |
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 41 |
Plant Area |
98,500
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $85,938 | 1,288,087 |
kWh
|
$0.067 |
Electricity Demand | $30,644 | 4,534 |
kW-mo/yr
|
$6.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,832 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,262 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,460 | $65,755 |
$9,577
142,939
kWh
|
$2,883
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,558 | $1,105 |
$2,558
38,181
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,371 | $1,560 |
$1,498
22,364
kWh
|
$873
-
kW-mo/yr
|
- | |
04 | 2.7131: Add area lighting switches | $571 | $2,910 |
$571
8,518
kWh
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $448 | - |
$182
2,719
kWh
|
$266
-
kW-mo/yr
|
- | |
06 | 3.5318: Recycle fluorescent lamps | $1,424 | $3,496 | - | - |
$1,424
-
lb
|
|
TOTAL RECOMMENDED | $19,832 | $74,826 |
$14,386
214,721
kWh
|
$4,022
-
kW-mo/yr
|
$1,424
-
lb
|
||
TOTAL IMPLEMENTED | $19,262 | $71,916 |
$13,816
206,203
kWh
|
$4,022
-
kW-mo/yr
|
$1,424
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs