| Assessment Year | 1998 |
|---|---|
| Principal Product | Reprocessed Textiles for Industrial Use |
| NAICS |
n/a
|
| SIC | 3053: Gaskets, Packing, and Sealing Devices |
| Sales Range | $5 M to 10M |
| # of Employees | 56 |
| Plant Area |
191,000
ft2
|
| Annual Production | 36,000,000
lb
|
| Production Hrs. Annual | 4,800
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $249,526 | 5,733,001 |
kWh
|
$0.044 |
| Electricity Demand | $265,041 | 19,691 |
kW-mo/yr
|
$13.46 |
| Fuel Oil #2 | $7,702 | 2,076 |
MMBtu
|
$3.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,799 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,209 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $9,368 | $24,200 | - |
$9,368
-
kW-mo/yr
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $586 | $458 |
$586
9,086
kWh
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $623 | $25 |
$623
9,672
kWh
|
- | - | |
| 04 | 2.7231: Use radiant heater for spot heating | $902 | $1,975 | - | - |
$902
-
MMBtu
|
|
| 05 | 2.7293: Install dry sprinkler system or other method to reduce heating requirements | $2,320 | $9,100 |
$1,549
24,033
kWh
|
$771
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $13,799 | $35,758 |
$2,758
42,791
kWh
|
$10,139
-
kW-mo/yr
|
$902
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,209 | $483 |
$1,209
18,758
kWh
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs