ITAC Assessment: MA0411
ITAC logo
ITAC Assessment: MA0411
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product metal and wood chairs
NAICS
n/a
SIC 2599: Furniture and Fixtures, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 252
Plant Area 303,600
ft2
Annual Production 306,800
pieces
Production Hrs. Annual 3,000
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $133,917 2,052,462
kWh
Electricity Demand $119,007 8,214
kW-mo/yr
Natural Gas $97,294 19,341
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $187,372 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,473

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Raw Material Savings
01 3.5311: Recover and reuse waste material $171,700 $200,000 - - - $171,700
02 2.7111: Reduce illumination to minimum necessary levels $7,333 $225 $3,595
55,100
kWh
$3,477
-
kW-mo/yr
$261 -
03 3.6193: Install equipment (eg compactor) to reduce disposal costs $7,128 $9,975 - - $7,128 -
04 2.4221: Install compressor air intakes in coolest locations $631 $517 $631
9,086
kWh
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $440 $255 $440
6,741
kWh
- - -
06 2.7135: Install occupancy sensors $140 $140 $140
2,052
kWh
- - -
TOTAL RECOMMENDED $187,372 $211,112 $4,806
72,979
kWh
$3,477
-
kW-mo/yr
$7,389 $171,700
TOTAL IMPLEMENTED $7,473 $365 $3,735
57,152
kWh
$3,477
-
kW-mo/yr
$261 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs