| Assessment Year | 1998 |
|---|---|
| Principal Product | metal and wood chairs |
| NAICS |
n/a
|
| SIC | 2599: Furniture and Fixtures, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 252 |
| Plant Area |
303,600
ft2
|
| Annual Production | 306,800
pieces
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $133,917 | 2,052,462 |
kWh
|
$0.065 |
| Electricity Demand | $119,007 | 8,214 |
kW-mo/yr
|
$14.49 |
| Natural Gas | $97,294 | 19,341 |
MMBtu
|
$5.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $187,372 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,473 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.5311: Recover and reuse waste material | $171,700 | $200,000 | - | - | - | $171,700 | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $7,333 | $225 |
$3,595
55,100
kWh
|
$3,477
-
kW-mo/yr
|
$261 | - | |
| 03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $7,128 | $9,975 | - | - | $7,128 | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $631 | $517 |
$631
9,086
kWh
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $440 | $255 |
$440
6,741
kWh
|
- | - | - | |
| 06 | 2.7135: Install occupancy sensors | $140 | $140 |
$140
2,052
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $187,372 | $211,112 |
$4,806
72,979
kWh
|
$3,477
-
kW-mo/yr
|
$7,389 | $171,700 | ||
| TOTAL IMPLEMENTED | $7,473 | $365 |
$3,735
57,152
kWh
|
$3,477
-
kW-mo/yr
|
$261 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs