ITAC Assessment: MA0406
ITAC logo
ITAC Assessment: MA0406
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Metal Bellows Seals
NAICS
n/a
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $10
M
to 50
M
# of Employees 185
Plant Area 55,600
ft2
Annual Production 65,000
pieces
Production Hrs. Annual 5,200
hrs
Location (State) Rhode Island

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $153,615 2,243,259
kWh
Electricity Demand $43,294 8,184
kW-mo/yr
Natural Gas $32,018 4,030
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,635 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,615

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
01 2.8113: Purchase gas directly from a contract gas supplier $3,022 $200 - - - - - $3,022 -
02 2.4224: Upgrade controls on compressors $3,950 $1,785 $3,950
43,669
kWh
- - - - - -
03 2.7221: Lower temperature during the winter season and vice-versa $1,323 $187 $1,323
20,223
kWh
- - - - - -
04 2.4221: Install compressor air intakes in coolest locations $802 $541 $802
9,086
kWh
- - - - - -
05 2.2437: Recover waste heat from equipment $1,955 $2,332 - - $1,955
-
MMBtu
- - - -
06 3.6112: Use filter and drying oven to reduce sludge volume $3,045 $14,790 $1,338
16,120
kWh
$571
-
kW-mo/yr
$(-489.0)
-
MMBtu
$1,625
-
gal
- - -
07 2.7232: Replace existing hvac unit with high efficiency model $3,468 $24,000 $2,108
22,274
kWh
- - - $1,360 - -
08 2.2614: Use cooling tower or economizer to replace chiller cooling $3,070 $13,540 $3,446
38,101
kWh
- - - - - $(-376.0)
-
Tgal
TOTAL RECOMMENDED $20,635 $57,375 $12,967
149,473
kWh
$571
-
kW-mo/yr
$1,466
-
MMBtu
$1,625
-
gal
$1,360 $3,022 $(-376.0)
-
Tgal
TOTAL IMPLEMENTED $8,615 $24,928 $4,233
51,583
kWh
- - - $1,360 $3,022 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs