Assessment Year | 1997 |
---|---|
Principal Product | Preforated Components |
NAICS |
n/a
|
SIC | 3649: |
Sales Range | $10 M to 50M |
# of Employees | 91 |
Plant Area |
114,700
ft2
|
Annual Production | 160,000,000
pieces
|
Production Hrs. Annual | 4,290
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Demand | $100,062 | 5,469 |
kW-mo/yr
|
$18.30 |
Natural Gas | $40,063 | 5,676 |
MMBtu
|
$7.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,779 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,492 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,044 | $600 |
$5,044
82,356
kWh
|
- | - | - | |
02 | 2.8113: Purchase gas directly from a contract gas supplier | $3,025 | $200 | - | - | - | $3,025 | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,200 | - |
$1,200
19,050
kWh
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $874 | $681 |
$874
13,775
kWh
|
- | - | - | |
05 | 2.6218: Turn off equipment when not in use | $790 | $404 | - | - |
$790
-
MMBtu
|
- | |
06 | 2.7131: Add area lighting switches | $413 | $60 |
$335
5,275
kWh
|
$78
-
kW-mo/yr
|
- | - | |
07 | 4.821: Pay bills on time to avoid late fees | $433 | - | - | - | - | $433 | |
TOTAL RECOMMENDED | $11,779 | $1,945 |
$7,453
120,456
kWh
|
$78
-
kW-mo/yr
|
$790
-
MMBtu
|
$3,458 | ||
TOTAL IMPLEMENTED | $10,492 | $1,204 |
$6,244
101,406
kWh
|
- |
$790
-
MMBtu
|
$3,458 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs