Assessment Year | 1997 |
---|---|
Principal Product | high quality converted papers |
NAICS |
n/a
|
SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 101 |
Plant Area |
310,000
ft2
|
Annual Production | 20,000,000
lb
|
Production Hrs. Annual | 5,880
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $291,467 | 5,038,101 |
kWh
|
$0.058 |
Electricity Demand | $148,862 | 13,975 |
kW-mo/yr
|
$10.65 |
Natural Gas | $13,984 | 3,024 |
MMBtu
|
$4.62 |
Fuel Oil #2 | $124,228 | 24,065 |
MMBtu
|
$5.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,295 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,507 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.4145: Use magnetic technology to treat water | $7,580 | $9,347 | - | - | - | - |
$3,790
-
gal
|
$3,790
-
lb
|
|
02 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $5,492 | $11,700 | - | - |
$2,746
-
MMBtu
|
$2,746
-
MMBtu
|
- | - | |
03 | 2.2612: Use cooling tower water instead of refrigeration | $4,207 | $14,329 |
$4,207
67,702
kWh
|
- | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,606 | $75 |
$2,606
44,842
kWh
|
- | - | - | - | - | |
05 | 2.6218: Turn off equipment when not in use | $1,409 | $60 |
$947
15,240
kWh
|
$462
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $819 | $102 |
$819
13,189
kWh
|
- | - | - | - | - | |
07 | 2.6218: Turn off equipment when not in use | $182 | $132 |
$182
2,931
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $22,295 | $35,745 |
$8,761
143,904
kWh
|
$462
-
kW-mo/yr
|
$2,746
-
MMBtu
|
$2,746
-
MMBtu
|
$3,790
-
gal
|
$3,790
-
lb
|
||
TOTAL IMPLEMENTED | $9,507 | $11,835 |
$3,553
60,082
kWh
|
$462
-
kW-mo/yr
|
$2,746
-
MMBtu
|
$2,746
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs