Assessment Year | 2011 |
---|---|
Principal Product | Motor Vehicles |
NAICS | 336111: Automobile Manufacturing |
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | greater than $500 M |
# of Employees | 30 |
Plant Area |
1,800,000
ft2
|
Annual Production | 999,999,999
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Delaware |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $960,000 | 12,000,000 |
kWh
|
$0.080 |
Natural Gas | $226,270 | 18,700 |
MMBtu
|
$12.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $554,674 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $186,359 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $14,500 | $200 |
$14,500
181,000
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,200 | $3,200 |
$15,200
190,800
kWh
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $51,300 | $12,000 |
$51,300
641,700
kWh
|
- | |
04 | 2.4239: Eliminate or reduce compressed air usage | $182,000 | $17,000 |
$182,000
2,280,000
kWh
|
- | |
05 | 2.1231: Establish burner maintenance schedule for boilers | $21,659 | $4,300 | - |
$21,659
-
MMBtu
|
|
06 | 2.2122: Install / repair insulation on condensate lines | $51,400 | $10,000 | - |
$51,400
-
MMBtu
|
|
07 | 2.2414: Use waste heat from hot flue gases to preheat | $3,315 | $15,000 | - |
$3,315
-
MMBtu
|
|
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $183,000 | $600,000 |
$183,000
2,290,000
kWh
|
- | |
09 | 2.7124: Make a practice of turning off lights when not needed | $32,300 | $200 |
$32,300
404,100
kWh
|
- | |
TOTAL RECOMMENDED | $554,674 | $661,900 |
$478,300
5,987,600
kWh
|
$76,374
-
MMBtu
|
||
TOTAL IMPLEMENTED | $186,359 | $29,900 |
$113,300
1,417,600
kWh
|
$73,059
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs