Assessment Year | 1997 |
---|---|
Principal Product | electronic components |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 500 |
Plant Area |
320,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Demand | $582,832 | 34,518 |
kW-mo/yr
|
$16.88 |
Natural Gas | $105,512 | 18,857 |
MMBtu
|
$5.60 |
Fuel Oil #4 | $59,998 | 14,413 |
MMBtu
|
$4.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $361,610 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $352,927 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.521: Clear and rent existing space | $262,500 | - | - | - | - | $262,500 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $89,097 | $320,340 |
$63,991
971,571
kWh
|
$25,106
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,317 | $24,908 |
$2,778
43,083
kWh
|
$1,539
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,246 | $4,225 |
$2,333
35,463
kWh
|
$913
-
kW-mo/yr
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,330 | $271 |
$1,330
20,223
kWh
|
- | - | - | |
06 | 3.1175: Use a different or recycled raw material | $1,120 | - | - | - |
$1,120
-
lb
|
- | |
TOTAL RECOMMENDED | $361,610 | $349,744 |
$70,432
1,070,340
kWh
|
$27,558
-
kW-mo/yr
|
$1,120
-
lb
|
$262,500 | ||
TOTAL IMPLEMENTED | $352,927 | $320,611 |
$65,321
991,794
kWh
|
$25,106
-
kW-mo/yr
|
- | $262,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs