Assessment Year | 1996 |
---|---|
Principal Product | Corrugated Cardboard |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 159 |
Plant Area |
162,616
ft2
|
Annual Production | 480,000
thousand feet
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $235,103 | 2,783,998 |
kWh
|
$0.084 |
Natural Gas | $107,554 | 26,667 |
MMBtu
|
$4.03 |
LPG | $18,262 | 2,122 |
MMBtu
|
$8.61 |
Fuel Oil #2 | $44,826 | 10,004 |
MMBtu
|
$4.48 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,988 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $6,197 | $3,178 | - |
$3,983
-
MMBtu
|
$2,214
-
MMBtu
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $413 | $272 |
$413
7,034
kWh
|
- | - | - | |
03 | 2.2437: Recover waste heat from equipment | $1,699 | $1,415 |
$924
15,240
kWh
|
$498
-
MMBtu
|
$277
-
MMBtu
|
- | |
04 | 2.7231: Use radiant heater for spot heating | $2,379 | $3,200 | - |
$1,529
-
MMBtu
|
$850
-
MMBtu
|
- | |
05 | 3.4145: Use magnetic technology to treat water | $3,300 | $9,235 | - | - | - |
$3,300
-
gal
|
|
TOTAL RECOMMENDED | $13,988 | $17,300 |
$1,337
22,274
kWh
|
$6,010
-
MMBtu
|
$3,341
-
MMBtu
|
$3,300
-
gal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs