Assessment Year | 1996 |
---|---|
Principal Product | Molded Plywood and Plastic Extrusions |
NAICS |
n/a
|
SIC | 2431: Millwork |
Sales Range | $5 M to 10M |
# of Employees | 61 |
Plant Area |
54,775
ft2
|
Annual Production | 24,000,000
thousand feet
|
Production Hrs. Annual | 8,710
hrs
|
Location (State) | New Hampshire |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $208,383 | 2,429,367 |
kWh
|
$0.086 |
Electricity Demand | $58,684 | 7,600 |
kW-mo/yr
|
$7.72 |
Electricity Fees | $4,144 | - |
|
- |
Natural Gas | $15,935 | 2,547 |
MMBtu
|
$6.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,367 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,959 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,510 | $48,558 |
$7,824
89,097
kWh
|
$1,686
-
kW-mo/yr
|
- | |
02 | 2.6218: Turn off equipment when not in use | $7,694 | - |
$7,694
90,856
kWh
|
- | - | |
03 | 2.3137: Use power during off-peak periods | $7,680 | - | - |
$7,680
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,549 | $325 |
$2,549
33,998
kWh
|
- | - | |
05 | 2.4321: Upgrade obsolete equipment | $1,801 | $4,300 |
$1,801
20,223
kWh
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $723 | $700 |
$723
8,206
kWh
|
- | - | |
07 | 3.6192: Use a less expensive method of waste removal | $410 | - | - | - | $410 | |
TOTAL RECOMMENDED | $30,367 | $53,883 |
$20,591
242,380
kWh
|
$9,366
-
kW-mo/yr
|
$410 | ||
TOTAL IMPLEMENTED | $2,959 | $325 |
$2,549
33,998
kWh
|
- | $410 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs