| Assessment Year | 1995 |
|---|---|
| Principal Product | reflow ovens |
| NAICS |
n/a
|
| SIC | 3567: Industrial Process Furnaces and Ovens |
| Sales Range | $10 M to 50M |
| # of Employees | 98 |
| Plant Area |
33,000
ft2
|
| Annual Production | 250
pieces
|
| Production Hrs. Annual | 4,862
hrs
|
| Location (State) | New Hampshire |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,047 | 565,358 |
kWh
|
$0.12 |
| LPG | $19,324 | 1,955 |
MMBtu
|
$9.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $68,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,351 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $6,107 | $2,446 |
$177
2,052
kWh
|
$5,930
-
MMBtu
|
- | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,398 | $24,197 |
$5,398
47,479
kWh
|
- | - | - | - | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $2,909 | - |
$2,909
32,532
kWh
|
- | - | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,098 | $798 |
$1,098
9,965
kWh
|
- | - | - | - | - | |
| 05 | 2.8114: Change rate schedules or other changes in utility service | $598 | - | - | - | - | $598 | - | - | |
| 06 | 2.7314: Reduce ventilation air | $344 | - |
$46
586
kWh
|
$298
-
MMBtu
|
- | - | - | - | |
| 07 | 3.1162: Use less wasteful packaging | $22,500 | - | - | - | - | - | $22,500 | - | |
| 08 | 3.2121: Convert to electrostatic powder coating | $16,229 | $4,500 | - | - | - | - | $16,229 | - | |
| 09 | 3.1191: Change procedures / equipment / operating conditions | $11,867 | $5,000 |
$(-1,276.0)
(-6,155)
kWh
|
- | - | - | - | $13,143 | |
| 10 | 3.6192: Use a less expensive method of waste removal | $1,920 | - | - | - |
$1,920
-
lb
|
- | - | - | |
| TOTAL RECOMMENDED | $68,970 | $36,941 |
$8,352
86,459
kWh
|
$6,228
-
MMBtu
|
$1,920
-
lb
|
$598 | $38,729 | $13,143 | ||
| TOTAL IMPLEMENTED | $4,351 | $798 |
$4,053
43,083
kWh
|
$298
-
MMBtu
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs