| Assessment Year | 1995 |
|---|---|
| Principal Product | metal coating services |
| NAICS |
n/a
|
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 37 |
| Plant Area |
52,500
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $105,315 | 701,055 |
kWh
|
$0.15 |
| Natural Gas | $126,979 | 15,734 |
MMBtu
|
$8.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,441 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,249 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3137: Use power during off-peak periods | $4,800 | - |
$4,800
-
kWh
|
- | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $3,349 | $200 |
$3,349
33,705
kWh
|
- | - | |
| 03 | 2.7243: Improve air circulation with destratification fans / other methods | $2,634 | $5,995 |
$(-818.0)
(-9,965)
kWh
|
$3,452
-
MMBtu
|
- | |
| 04 | 2.8123: Pay utility bills on time | $1,820 | - | - | - | $1,820 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,369 | $2,464 |
$1,369
10,551
kWh
|
- | - | |
| 06 | 2.7314: Reduce ventilation air | $1,190 | $3,320 | - |
$1,190
-
MMBtu
|
- | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $753 | - |
$753
10,844
kWh
|
- | - | |
| 08 | 2.6212: Turn off equipment during breaks, reduce operating time | $612 | $330 |
$612
6,155
kWh
|
- | - | |
| 09 | 2.4221: Install compressor air intakes in coolest locations | $558 | $127 |
$558
4,689
kWh
|
- | - | |
| 10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $356 | $570 |
$356
2,931
kWh
|
- | - | |
| TOTAL RECOMMENDED | $17,441 | $13,006 |
$10,979
58,910
kWh
|
$4,642
-
MMBtu
|
$1,820 | ||
| TOTAL IMPLEMENTED | $14,249 | $6,884 |
$11,239
64,186
kWh
|
$1,190
-
MMBtu
|
$1,820 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs