| Assessment Year | 1994 |
|---|---|
| Principal Product | specialty wire brushes |
| NAICS |
n/a
|
| SIC | 3991: Brooms and Brushes |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
60,000
ft2
|
| Annual Production | 1,200,000
pieces
|
| Production Hrs. Annual | 4,271
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $126,987 | 1,159,144 |
kWh
|
$0.11 |
| Natural Gas | $15,626 | 2,125 |
MMBtu
|
$7.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $47,788 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $44,570 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.1331: Burn a less expensive grade of fuel | $29,061 | $21,690 |
$22,894
208,968
kWh
|
$6,167
-
MMBtu
|
|
| 02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $6,295 | $6,831 |
$6,295
57,444
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,696 | - |
$5,696
53,634
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,761 | $5,827 |
$2,761
25,205
kWh
|
- | |
| 05 | 2.7221: Lower temperature during the winter season and vice-versa | $2,190 | $2,829 | - |
$2,190
-
MMBtu
|
|
| 06 | 2.4221: Install compressor air intakes in coolest locations | $1,028 | $519 |
$1,028
9,379
kWh
|
- | |
| 07 | 2.2136: Install / repair insulation on steam lines | $757 | $434 | - |
$757
-
MMBtu
|
|
| TOTAL RECOMMENDED | $47,788 | $38,130 |
$38,674
354,630
kWh
|
$9,114
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $44,570 | $34,782 |
$37,646
345,251
kWh
|
$6,924
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs