Assessment Year | 1994 |
---|---|
Principal Product | specialty wire brushes |
NAICS |
n/a
|
SIC | 3991: Brooms and Brushes |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
60,000
ft2
|
Annual Production | 1,200,000
pieces
|
Production Hrs. Annual | 4,271
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $126,987 | 1,159,144 |
kWh
|
$0.11 |
Natural Gas | $15,626 | 2,125 |
MMBtu
|
$7.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,788 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $44,570 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1331: Burn a less expensive grade of fuel | $29,061 | $21,690 |
$22,894
208,968
kWh
|
$6,167
-
MMBtu
|
|
02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $6,295 | $6,831 |
$6,295
57,444
kWh
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,696 | - |
$5,696
53,634
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,761 | $5,827 |
$2,761
25,205
kWh
|
- | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $2,190 | $2,829 | - |
$2,190
-
MMBtu
|
|
06 | 2.4221: Install compressor air intakes in coolest locations | $1,028 | $519 |
$1,028
9,379
kWh
|
- | |
07 | 2.2136: Install / repair insulation on steam lines | $757 | $434 | - |
$757
-
MMBtu
|
|
TOTAL RECOMMENDED | $47,788 | $38,130 |
$38,674
354,630
kWh
|
$9,114
-
MMBtu
|
||
TOTAL IMPLEMENTED | $44,570 | $34,782 |
$37,646
345,251
kWh
|
$6,924
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs