ITAC Assessment: MA0294
ITAC logo
ITAC Assessment: MA0294
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Computer forms
NAICS
n/a
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 33,600
ft2
Annual Production 0
units
Production Hrs. Annual 5,876
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $79,243 793,669
kWh
LPG $5,798 574
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,763 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $615

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,312 - $2,312
23,154
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,287 $2,112 $1,287
12,896
kWh
03 2.4221: Install compressor air intakes in coolest locations $410 $91 $410
4,103
kWh
04 2.7135: Install occupancy sensors $263 $563 $263
2,638
kWh
05 2.4133: Use most efficient type of electric motors $286 $1,309 $286
2,931
kWh
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $205 - $205
2,052
kWh
TOTAL RECOMMENDED $4,763 $4,075 $4,763
47,774
kWh
TOTAL IMPLEMENTED $615 $91 $615
6,155
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs