| Assessment Year | 1994 |
|---|---|
| Principal Product | Turbine Blade and Vane Maint/Coating |
| NAICS |
n/a
|
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 270 |
| Plant Area |
132,500
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,992
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $490,274 | 6,419,988 |
kWh
|
$0.076 |
| Natural Gas | $287,830 | 41,442 |
MMBtu
|
$6.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $130,536 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,615 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8113: Purchase gas directly from a contract gas supplier | $100,844 | $54,704 | - | - | $100,844 | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $21,561 | $34,000 |
$33,973
444,900
kWh
|
$(-12,412.0)
-
MMBtu
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $2,149 | $644 |
$2,149
28,136
kWh
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $491 | $100 |
$491
8,792
kWh
|
- | - | |
| 05 | 2.7224: Reduce space conditioning during non-working hours | $1,467 | $982 | - |
$1,467
-
MMBtu
|
- | |
| 06 | 2.2511: Insulate bare equipment | $1,209 | $334 |
$1,209
15,826
kWh
|
- | - | |
| 07 | 2.7135: Install occupancy sensors | $1,007 | $218 |
$1,007
13,189
kWh
|
- | - | |
| 08 | 2.7221: Lower temperature during the winter season and vice-versa | $769 | - | - |
$769
-
MMBtu
|
- | |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $739 | - |
$739
9,672
kWh
|
- | - | |
| 10 | 2.4131: Size electric motors for peak operating efficiency | $300 | $961 |
$300
3,517
kWh
|
- | - | |
| TOTAL RECOMMENDED | $130,536 | $91,943 |
$39,868
524,032
kWh
|
$(-10,176.0)
-
MMBtu
|
$100,844 | ||
| TOTAL IMPLEMENTED | $5,615 | $1,726 |
$3,379
46,600
kWh
|
$2,236
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs