ITAC Assessment: MA0281
ITAC logo
ITAC Assessment: MA0281
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Optic single vision eye
NAICS
n/a
SIC 3851: Ophthalmic Goods
Sales Range $5
M
to 10
M
# of Employees 52
Plant Area 57,000
ft2
Annual Production 1,600,000
pieces
Production Hrs. Annual 2,205
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $111,913 977,433
kWh
Fuel Oil #4 $18,216 3,947
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,553 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,040

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings
01 2.3212: Optimize plant power factor $8,868 $12,000 $8,868
-
kWh
-
02 2.4224: Upgrade controls on compressors $5,907 $4,000 $5,907
51,583
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,920 $3,492 $2,920
25,498
kWh
-
04 2.1233: Analyze flue gas for proper air/fuel ratio $1,872 $400 - $1,872
-
MMBtu
05 2.2511: Insulate bare equipment $1,812 $320 $1,812
15,826
kWh
-
06 2.2511: Insulate bare equipment $470 $387 $470
4,103
kWh
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $436 - $436
3,810
kWh
-
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $268 $80 $268
2,345
kWh
-
TOTAL RECOMMENDED $22,553 $20,679 $20,681
103,165
kWh
$1,872
-
MMBtu
TOTAL IMPLEMENTED $7,040 $4,212 $5,168
45,134
kWh
$1,872
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs