ITAC Assessment: MA0261
ITAC logo
ITAC Assessment: MA0261
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product "Printed Circuit Boards"
NAICS
n/a
SIC 3672: Printed Circuit Boards
Sales Range $1
M
to 5
M
# of Employees 38
Plant Area 30,000
ft2
Annual Production 47
thousand feet
Production Hrs. Annual 6,552
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,399 811,547
kWh
Natural Gas $17,647 2,420
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,385 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,292

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.2511: Insulate bare equipment $2,590 $525 $2,590
31,653
kWh
02 2.7111: Reduce illumination to minimum necessary levels $1,990 $322 $1,990
24,326
kWh
03 2.7226: Use computer programs to optimize hvac performance $1,271 - $1,271
15,533
kWh
04 2.7241: Install outside air damper / economizer on hvac unit $1,031 $4,000 $1,031
12,603
kWh
05 2.4221: Install compressor air intakes in coolest locations $288 $48 $288
3,517
kWh
06 2.7142: Utilize higher efficiency lamps and/or ballasts $215 $80 $215
2,638
kWh
TOTAL RECOMMENDED $7,385 $4,975 $7,385
90,270
kWh
TOTAL IMPLEMENTED $4,292 $4,322 $4,292
52,462
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs