Assessment Year | 1991 |
---|---|
Principal Product | LATEX FOAM MATTRESSES |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 119 |
Plant Area |
n/a
|
Annual Production | 19,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $506,670 | 5,998,828 |
kWh
|
$0.084 |
Natural Gas | $122,795 | 48,541 |
MMBtu
|
$2.53 |
Fuel Oil #6 | $88,280 | 4,134,248 |
MMBtu
|
$0.021 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,184 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,530 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1332: Convert combustion equipment to burn natural gas | $27,069 | - | - |
$50,532
-
MMBtu
|
$(-23,463.0)
-
MMBtu
|
- | |
02 | 2.2694: Use highest temperature for chilling or cold storage | $8,647 | $5,000 |
$8,647
102,286
kWh
|
- | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,534 | $2,000 |
$6,534
77,374
kWh
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,585 | $15,000 |
$3,836
45,428
kWh
|
- | - | $(-251.0) | |
05 | 2.4221: Install compressor air intakes in coolest locations | $891 | $400 |
$891
10,551
kWh
|
- | - | - | |
06 | 2.2511: Insulate bare equipment | $458 | $430 | - |
$458
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $47,184 | $22,830 |
$19,908
235,639
kWh
|
$50,990
-
MMBtu
|
$(-23,463.0)
-
MMBtu
|
$(-251.0) | ||
TOTAL IMPLEMENTED | $16,530 | $7,830 |
$16,072
190,211
kWh
|
$458
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs