ITAC Assessment: MA0228
ITAC logo
ITAC Assessment: MA0228
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product LATEX FOAM MATTRESSES
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 119
Plant Area
n/a
Annual Production 19,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $506,670 5,998,828
kWh
Natural Gas $122,795 48,541
MMBtu
Fuel Oil #6 $88,280 4,134,248
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,184 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,530

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #6 Savings Administrative Changes Savings
01 2.1332: Convert combustion equipment to burn natural gas $27,069 - - $50,532
-
MMBtu
$(-23,463.0)
-
MMBtu
-
02 2.2694: Use highest temperature for chilling or cold storage $8,647 $5,000 $8,647
102,286
kWh
- - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,534 $2,000 $6,534
77,374
kWh
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,585 $15,000 $3,836
45,428
kWh
- - $(-251.0)
05 2.4221: Install compressor air intakes in coolest locations $891 $400 $891
10,551
kWh
- - -
06 2.2511: Insulate bare equipment $458 $430 - $458
-
MMBtu
- -
TOTAL RECOMMENDED $47,184 $22,830 $19,908
235,639
kWh
$50,990
-
MMBtu
$(-23,463.0)
-
MMBtu
$(-251.0)
TOTAL IMPLEMENTED $16,530 $7,830 $16,072
190,211
kWh
$458
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Fuel Oil #6 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs