ITAC Assessment: MA0197
ITAC logo
ITAC Assessment: MA0197
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product INJECTION MOLDED PARTS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 57
Plant Area
n/a
Annual Production 300,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $169,911 2,206,038
kWh
Natural Gas $25,921 4,083
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,537 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,898

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $406 $142 $406
5,275
kWh
-
02 2.7224: Reduce space conditioning during non-working hours $1,166 $642 $1,004
13,189
kWh
$162
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,726 $10,622 $6,726
87,339
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $948 $5,052 $948
12,309
kWh
-
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $972 - $972
-
kWh
-
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,680 $927 $2,505
32,532
kWh
$(-825.0)
-
MMBtu
07 2.7492: Use proper thickness of insulation on building envelope $6,639 $19,720 $1,083
14,068
kWh
$5,556
-
MMBtu
TOTAL RECOMMENDED $18,537 $37,105 $13,644
164,712
kWh
$4,893
-
MMBtu
TOTAL IMPLEMENTED $11,898 $17,385 $12,561
150,644
kWh
$(-663.0)
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs