Assessment Year | 1990 |
---|---|
Principal Product | INJECTION MOLDED PARTS |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 57 |
Plant Area |
n/a
|
Annual Production | 300,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $169,911 | 2,206,038 |
kWh
|
$0.077 |
Natural Gas | $25,921 | 4,083 |
MMBtu
|
$6.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,537 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,898 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $406 | $142 |
$406
5,275
kWh
|
- | |
02 | 2.7224: Reduce space conditioning during non-working hours | $1,166 | $642 |
$1,004
13,189
kWh
|
$162
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,726 | $10,622 |
$6,726
87,339
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $948 | $5,052 |
$948
12,309
kWh
|
- | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $972 | - |
$972
-
kWh
|
- | |
06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,680 | $927 |
$2,505
32,532
kWh
|
$(-825.0)
-
MMBtu
|
|
07 | 2.7492: Use proper thickness of insulation on building envelope | $6,639 | $19,720 |
$1,083
14,068
kWh
|
$5,556
-
MMBtu
|
|
TOTAL RECOMMENDED | $18,537 | $37,105 |
$13,644
164,712
kWh
|
$4,893
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,898 | $17,385 |
$12,561
150,644
kWh
|
$(-663.0)
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs