Assessment Year | 1990 |
---|---|
Principal Product | CABLES FOR COMPUTERS |
NAICS |
n/a
|
SIC | 3357: Drawing and Insulating of Nonferrous Wire |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
n/a
|
Annual Production | 6,500,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $353,012 | 4,646,835 |
kWh
|
$0.076 |
Fuel Oil #2 | $64,829 | 12,489 |
MMBtu
|
$5.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,050 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,148 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $3,539 | $1,600 |
$3,539
46,600
kWh
|
- | - | |
02 | 2.2437: Recover waste heat from equipment | $10,203 | $1,196 | - |
$10,203
-
MMBtu
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,675 | - |
$4,675
61,547
kWh
|
- | - | |
04 | 2.2531: Re-size charging openings or add movable cover or door | $245 | $95 |
$245
3,224
kWh
|
- | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $12,162 | $31,800 |
$12,162
-
kWh
|
- | - | |
06 | 2.6232: Install set-back timers | $4,808 | $1,521 |
$4,808
63,306
kWh
|
- | - | |
07 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $4,956 | $9,900 |
$1,157
15,240
kWh
|
- | $3,799 | |
08 | 2.2511: Insulate bare equipment | $462 | $631 | - |
$462
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $41,050 | $46,743 |
$26,586
189,917
kWh
|
$10,665
-
MMBtu
|
$3,799 | ||
TOTAL IMPLEMENTED | $20,148 | $3,348 |
$9,483
124,853
kWh
|
$10,665
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs