Assessment Year | 1988 |
---|---|
Principal Product | MILK |
NAICS |
n/a
|
SIC | 2026: Fluid Milk |
Sales Range | $5 M to 10M |
# of Employees | 65 |
Plant Area |
n/a
|
Annual Production | 32,000,000
lb
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,935 | 1,070,926 |
kWh
|
$0.049 |
Natural Gas | $38,344 | 8,213 |
MMBtu
|
$4.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,884 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,713 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $312 | - |
$312
6,448
kWh
|
- | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,855 | $300 | - |
$1,855
-
MMBtu
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $5,627 | $1,502 | - |
$5,627
-
MMBtu
|
- | |
04 | 2.2122: Install / repair insulation on condensate lines | $298 | $72 | - |
$298
-
MMBtu
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $117 | $107 |
$117
2,345
kWh
|
- | - | |
06 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $1,519 | $5,000 | - |
$1,519
-
MMBtu
|
- | |
07 | 2.1213: Direct warmest air to combustion intake | $231 | $500 | - |
$231
-
MMBtu
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $283 | $17 |
$270
5,569
kWh
|
- | $13 | |
09 | 2.2437: Recover waste heat from equipment | $14,642 | $20,720 | - |
$14,642
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $24,884 | $28,218 |
$699
14,362
kWh
|
$24,172
-
MMBtu
|
$13 | ||
TOTAL IMPLEMENTED | $9,713 | $6,926 |
$699
14,362
kWh
|
$9,001
-
MMBtu
|
$13 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs