ITAC Assessment: OR0025
ITAC logo
ITAC Assessment: OR0025
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product MILK
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $5
M
to 10
M
# of Employees 65
Plant Area
n/a
Annual Production 32,000,000
lb
Production Hrs. Annual 4,420
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,935 1,070,926
kWh
Natural Gas $38,344 8,213
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,884 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,713

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $312 - $312
6,448
kWh
- -
02 2.1233: Analyze flue gas for proper air/fuel ratio $1,855 $300 - $1,855
-
MMBtu
-
03 2.2136: Install / repair insulation on steam lines $5,627 $1,502 - $5,627
-
MMBtu
-
04 2.2122: Install / repair insulation on condensate lines $298 $72 - $298
-
MMBtu
-
05 2.4133: Use most efficient type of electric motors $117 $107 $117
2,345
kWh
- -
06 2.1131: Repair faulty insulation in furnaces, boilers, etc $1,519 $5,000 - $1,519
-
MMBtu
-
07 2.1213: Direct warmest air to combustion intake $231 $500 - $231
-
MMBtu
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $283 $17 $270
5,569
kWh
- $13
09 2.2437: Recover waste heat from equipment $14,642 $20,720 - $14,642
-
MMBtu
-
TOTAL RECOMMENDED $24,884 $28,218 $699
14,362
kWh
$24,172
-
MMBtu
$13
TOTAL IMPLEMENTED $9,713 $6,926 $699
14,362
kWh
$9,001
-
MMBtu
$13
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs