Assessment Year | 1990 |
---|---|
Principal Product | RUBBER COATED PRODUCTS |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 55 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,750
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $80,225 | 992,966 |
kWh
|
$0.081 |
Fuel Oil #6 | $117,003 | 34,352 |
MMBtu
|
$3.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,380 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,863 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7229: Air condition only space necessary | $7,209 | $7,000 | - |
$7,209
-
MMBtu
|
- | |
02 | 2.2113: Repair or replace steam traps | $4,449 | $1,600 | - |
$5,889
-
MMBtu
|
$(-1,440.0) | |
03 | 2.2136: Install / repair insulation on steam lines | $6,213 | $2,557 | - |
$6,213
-
MMBtu
|
- | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $2,823 | $185 | - |
$2,823
-
MMBtu
|
- | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $1,378 | $245 | - |
$1,378
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $785 | $2,400 |
$785
9,672
kWh
|
- | - | |
07 | 2.6232: Install set-back timers | $308 | $677 |
$308
3,810
kWh
|
- | - | |
08 | 2.2122: Install / repair insulation on condensate lines | $215 | $545 | - |
$215
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $23,380 | $15,209 |
$1,093
13,482
kWh
|
$23,727
-
MMBtu
|
$(-1,440.0) | ||
TOTAL IMPLEMENTED | $15,863 | $7,532 |
$785
9,672
kWh
|
$16,518
-
MMBtu
|
$(-1,440.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs