ITAC Assessment: MA0188
ITAC logo
ITAC Assessment: MA0188
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product RUBBER COATED PRODUCTS
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,750
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $80,225 992,966
kWh
Fuel Oil #6 $117,003 34,352
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,380 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,863

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #6 Savings Administrative Changes Savings
01 2.7229: Air condition only space necessary $7,209 $7,000 - $7,209
-
MMBtu
-
02 2.2113: Repair or replace steam traps $4,449 $1,600 - $5,889
-
MMBtu
$(-1,440.0)
03 2.2136: Install / repair insulation on steam lines $6,213 $2,557 - $6,213
-
MMBtu
-
04 2.7221: Lower temperature during the winter season and vice-versa $2,823 $185 - $2,823
-
MMBtu
-
05 2.2414: Use waste heat from hot flue gases to preheat $1,378 $245 - $1,378
-
MMBtu
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $785 $2,400 $785
9,672
kWh
- -
07 2.6232: Install set-back timers $308 $677 $308
3,810
kWh
- -
08 2.2122: Install / repair insulation on condensate lines $215 $545 - $215
-
MMBtu
-
TOTAL RECOMMENDED $23,380 $15,209 $1,093
13,482
kWh
$23,727
-
MMBtu
$(-1,440.0)
TOTAL IMPLEMENTED $15,863 $7,532 $785
9,672
kWh
$16,518
-
MMBtu
$(-1,440.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #6 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs