| Assessment Year | 1989 |
|---|---|
| Principal Product | FILTER MEMBRANES |
| NAICS |
n/a
|
| SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $303,612 | 4,745,897 |
kWh
|
$0.064 |
| Natural Gas | $24,028 | 4,268 |
MMBtu
|
$5.63 |
| Fuel Oil #2 | $104,740 | 25,760 |
MMBtu
|
$4.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,428 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,531 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Fuel Oil #4 Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $5,228 | $426 |
$5,228
81,770
kWh
|
- | - | - | |
| 02 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $1,218 | $305 |
$1,218
19,050
kWh
|
- | - | - | |
| 03 | 2.7291: Reschedule and rearrange multiple-source heating systems | $4,308 | $243 | - |
$11,737
-
MMBtu
|
$(-7,429.0)
-
MMBtu
|
- | |
| 04 | 2.1331: Burn a less expensive grade of fuel | $12,509 | $15,150 | - | - |
$104,967
-
MMBtu
|
$(-92,458.0)
-
MMBtu
|
|
| 05 | 2.1213: Direct warmest air to combustion intake | $1,022 | $593 | - | - | - |
$1,022
-
MMBtu
|
|
| 06 | 2.2428: Use flue gases in radiant heater for space heating, ovens, etc | $1,093 | $592 | - | - | - |
$1,093
-
MMBtu
|
|
| 07 | 2.2437: Recover waste heat from equipment | $2,050 | $3,150 | - | - | - |
$2,050
-
MMBtu
|
|
| TOTAL RECOMMENDED | $27,428 | $20,459 |
$6,446
100,820
kWh
|
$11,737
-
MMBtu
|
$97,538
-
MMBtu
|
$(-88,293.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,531 | $15,743 | - | - |
$104,967
-
MMBtu
|
$(-91,436.0)
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Fuel Oil #4 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs