ITAC Assessment: MA0139
ITAC logo
ITAC Assessment: MA0139
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product FILTRATION EQUIPMENT
NAICS
n/a
SIC 3569: General Industrial Machinery and Equipment, Not Elsewhere
Sales Range $10
M
to 50
M
# of Employees 331
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,120
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $677,212 10,063,013
kWh
Fuel Oil #2 $68,035 15,960
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $64,598 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,909

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Fuel Oil #2 Savings
01 2.7261: Install timers and/or thermostats $6,928 $2,859 $2,465
36,635
kWh
- $4,463
-
MMBtu
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $7,534 $85,000 $24,796
368,406
kWh
$(-17,262.0)
-
MMBtu
-
03 2.3212: Optimize plant power factor $19,447 $9,000 $19,447
82,649
kWh
- -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $10,222 $3,943 $18,123
269,343
kWh
$(-7,901.0)
-
MMBtu
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $20,467 $72,797 $20,467
304,220
kWh
- -
TOTAL RECOMMENDED $64,598 $173,599 $85,298
1,061,253
kWh
$(-25,163.0)
-
MMBtu
$4,463
-
MMBtu
TOTAL IMPLEMENTED $33,909 $96,859 $46,708
487,690
kWh
$(-17,262.0)
-
MMBtu
$4,463
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs