ITAC Assessment: MA0133
ITAC logo
ITAC Assessment: MA0133
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product ALPINE SKIS
NAICS
n/a
SIC 3949: Sporting and Athletic Goods, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 150
Plant Area
n/a
Annual Production 70,000
pieces
Production Hrs. Annual 2,016
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $164,370 2,123,095
kWh
Natural Gas $45,244 7,191
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,018 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $19,753 $28,865 $30,232
390,680
kWh
$(-10,479.0)
-
MMBtu
02 2.2491: Use cooling air which cools hot work pieces for space heating $5,240 $8,712 - $5,240
-
MMBtu
03 2.2437: Recover waste heat from equipment $4,441 $5,370 - $4,441
-
MMBtu
04 2.6212: Turn off equipment during breaks, reduce operating time $3,359 - $3,359
43,376
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $930 $417 $930
12,016
kWh
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,586 $400 $2,586
33,411
kWh
-
07 2.7226: Use computer programs to optimize hvac performance $8,709 $3,000 $8,709
112,544
kWh
-
TOTAL RECOMMENDED $45,018 $46,764 $45,816
592,027
kWh
$(-798.0)
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs