ITAC Assessment: SD0478
ITAC logo
ITAC Assessment: SD0478
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Plastic Drums
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 47
Plant Area 71,000
ft2
Annual Production 850,000
pieces
Production Hrs. Annual 6,885
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $580,871 8,556,754
kWh
Electricity Demand $285,223 18,512
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $53,131 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,789

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 3.1192: Reduce scrap production $30,811 $12,465 $22,078
325,157
kWh
$8,733
-
kW-mo/yr
02 2.2614: Use cooling tower or economizer to replace chiller cooling $13,342 $32,990 $9,560
140,801
kWh
$3,782
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,128 $500 $2,958
43,581
kWh
$1,170
-
kW-mo/yr
04 2.7135: Install occupancy sensors $2,630 $2,535 $2,630
38,740
kWh
-
05 2.7134: Use photocell controls $2,220 $4,625 $1,853
27,291
kWh
$367
-
kW-mo/yr
TOTAL RECOMMENDED $53,131 $53,115 $39,079
575,570
kWh
$14,052
-
kW-mo/yr
TOTAL IMPLEMENTED $39,789 $20,125 $29,519
434,769
kWh
$10,270
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs