| Assessment Year | 1987 |
|---|---|
| Principal Product | COLD ROLLED STEEL STRIP |
| NAICS |
n/a
|
| SIC | 3316: Cold-Rolled Steel Sheet, Strip, and Bars |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
n/a
|
| Annual Production | 216,000
ton
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $659,544 | 7,137,749 |
kWh
|
$0.092 |
| Natural Gas | $256,628 | 50,032 |
MMBtu
|
$5.13 |
| Fuel Oil #4 | $53,557 | 11,232 |
MMBtu
|
$4.77 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $100,399 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $78,820 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,030 | $8,280 |
$10,030
90,856
kWh
|
- | - | |
| 02 | 2.2113: Repair or replace steam traps | $13,412 | - | - |
$14,672
-
MMBtu
|
$(-1,260.0) | |
| 03 | 2.2111: Install steam trap | $1,210 | $75 | - |
$1,210
-
MMBtu
|
- | |
| 04 | 2.7494: Install storm windows and doors | $10,280 | $11,000 | - |
$10,280
-
MMBtu
|
- | |
| 05 | 2.7261: Install timers and/or thermostats | $11,978 | $1,320 | - |
$11,978
-
MMBtu
|
- | |
| 06 | 2.3312: Install efficient rectifiers | $6,936 | $11,800 |
$6,936
58,030
kWh
|
- | - | |
| 07 | 2.4322: Use or replace with energy efficient substitutes | $13,433 | $17,320 |
$13,433
145,955
kWh
|
- | - | |
| 08 | 2.3191: Use demand controller or load shedder | $33,120 | $3,800 |
$33,120
-
kWh
|
- | - | |
| TOTAL RECOMMENDED | $100,399 | $53,595 |
$63,519
294,841
kWh
|
$38,140
-
MMBtu
|
$(-1,260.0) | ||
| TOTAL IMPLEMENTED | $78,820 | $24,400 |
$43,150
90,856
kWh
|
$36,930
-
MMBtu
|
$(-1,260.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs