ITAC Assessment: MA0066
ITAC logo
ITAC Assessment: MA0066
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product FABRICATED PLASTICS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 200
Plant Area
n/a
Annual Production 1,000,000
lb
Production Hrs. Annual 2,250
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,530 973,916
kWh
Natural Gas $20,910 3,485
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,562 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,146

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,416 $200 $1,416
16,706
kWh
-
02 2.4221: Install compressor air intakes in coolest locations $248 $200 $248
2,931
kWh
-
03 2.7494: Install storm windows and doors $474 $1,000 - $474
-
MMBtu
04 2.7224: Reduce space conditioning during non-working hours $5,424 - - $5,424
-
MMBtu
TOTAL RECOMMENDED $7,562 $1,400 $1,664
19,637
kWh
$5,898
-
MMBtu
TOTAL IMPLEMENTED $6,146 $1,200 $248
2,931
kWh
$5,898
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs