| Assessment Year | 1985 |
|---|---|
| Principal Product | COATED METAL PARTS |
| NAICS |
n/a
|
| SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| Sales Range | $1 M to 5M |
| # of Employees | 36 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $152,571 | 1,815,358 |
kWh
|
$0.084 |
| Natural Gas | $76,410 | 11,156 |
MMBtu
|
$6.85 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $21,805 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,143 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $1,045 | $300 |
$1,045
12,309
kWh
|
- | |
| 02 | 2.2437: Recover waste heat from equipment | $3,400 | $2,938 | - |
$3,400
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $892 | $112 |
$892
10,551
kWh
|
- | |
| 04 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $2,867 | $500 | - |
$2,867
-
MMBtu
|
|
| 05 | 2.2437: Recover waste heat from equipment | $10,939 | $2,229 | - |
$10,939
-
MMBtu
|
|
| 06 | 2.2437: Recover waste heat from equipment | $2,662 | $3,816 |
$(-79.0)
(-879)
kWh
|
$2,741
-
MMBtu
|
|
| TOTAL RECOMMENDED | $21,805 | $9,895 |
$1,858
21,981
kWh
|
$19,947
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $19,143 | $6,079 |
$1,937
22,860
kWh
|
$17,206
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs