| Assessment Year | 1984 |
|---|---|
| Principal Product | INDUSTRIAL PLASTIC |
| NAICS |
n/a
|
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $1 M to 5M |
| # of Employees | 70 |
| Plant Area |
n/a
|
| Annual Production | 380,000
lb
|
| Production Hrs. Annual | 6,528
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $105,658 | 1,403,869 |
kWh
|
$0.075 |
| LPG | $75 | 6 |
MMBtu
|
$12.50 |
| Fuel Oil #4 | $20,358 | 3,449 |
MMBtu
|
$5.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,906 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,906 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #4 Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $1,481 | $426 |
$1,738
23,154
kWh
|
$(-257.0)
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,985 | $548 |
$3,985
53,048
kWh
|
- | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $303 | $200 | - |
$303
-
MMBtu
|
|
| 04 | 2.2113: Repair or replace steam traps | $1,051 | $1,400 | - |
$1,051
-
MMBtu
|
|
| 05 | 2.4221: Install compressor air intakes in coolest locations | $86 | $185 |
$86
1,172
kWh
|
- | |
| TOTAL RECOMMENDED | $6,906 | $2,759 |
$5,809
77,374
kWh
|
$1,097
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $6,906 | $2,759 |
$5,809
77,374
kWh
|
$1,097
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs