ITAC Assessment: LT8407
ITAC logo
ITAC Assessment: LT8407
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Health and Eduaction
NAICS 813110: Religious Organizations
SIC 8062: General Medical and Surgical Hospitals
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 2,831,403
ft2
Annual Production 185
units
Production Hrs. Annual 8,760
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,163 909,655
kWh
Electricity Demand $2,404 2,223
kW-mo/yr
Waste Disposal Costs
Water Usage $14,999 4,573
Tgal
Water Disposal $45,410 4,573
Tgal
TOTAL YEARLY COSTS $158,976
RECOMMENDED SAVINGS* $8,603 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,664 $22,608 $6,664
63,045
kWh
-
02 2.7135: Install occupancy sensors $23 $83 $23
218
kWh
-
03 2.7444: Close holes and openings in building such as broken windows $1,916 $960 $1,898
17,961
kWh
$18
-
kW-mo/yr
TOTAL RECOMMENDED $8,603 $23,651 $8,585
81,224
kWh
$18
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs