| Assessment Year | 2023 |
|---|---|
| Principal Product | Frozen prepared fish |
| NAICS | 311710: Seafood Product Preparation and Packaging |
| SIC | 2092: Prepared Fresh or Frozen Fish and Seafoods |
| Sales Range | $5 M to 10M |
| # of Employees | 25 |
| Plant Area |
54,043
ft2
|
| Annual Production | 5,500,000
lb
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $245,063 | 2,445,500 |
kWh
|
$0.10 | |
| Electricity Fees | $23,799 | - |
|
- | |
| Natural Gas | $13,017 | 872 |
MMBtu
|
$14.93 | |
| Waste Disposal Costs | |||||
| Water Usage | $12,636 | 4,495 |
Tgal
|
$2.81 | |
| TOTAL YEARLY COSTS | $294,515 | ||||
| RECOMMENDED SAVINGS* | $39,763 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $2,120 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $14,178 | $61,016 |
$14,178
141,500
kWh
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,368 | $8,172 |
$3,368
33,613
kWh
|
|
| 03 | 2.7134: Use photocell controls | $731 | $328 |
$731
7,300
kWh
|
|
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $8,755 | $8,100 |
$8,755
87,377
kWh
|
|
| 05 | 2.2533: Replace air curtain doors with solid doors | $2,042 | $4,483 |
$2,042
20,381
kWh
|
|
| 06 | 2.7444: Close holes and openings in building such as broken windows | $2,120 | $600 |
$2,120
21,163
kWh
|
|
| 07 | 2.3112: Store heated/ cooled water for use during peak demand periods | $8,567 | $56,250 |
$8,567
85,500
kWh
|
|
| TOTAL RECOMMENDED | $39,763 | $138,949 |
$39,763
396,834
kWh
|
||
| TOTAL IMPLEMENTED | $2,120 | $600 |
$2,120
21,163
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs